A Unique History From My Work Diaries
Surveying Jobs
No4 Sub-Area, No4 Area, East Midlands Division, NCB from 1st January 1947
Page - 14 -
Jul 1958
Tues 1 … U/g … 60s and 110s dial surveys and measuring, 5 gates … 3 men (MS, RB, RE) - (395 + 22 u/g)
Wed 2 … Technical College … Field Trip to Dale Abbey cancelled.
Thurs 3 … 60s and 110s levels plotted. Scaling tracings for half year.
Fri 4 … Office … Typing levels etc. Progress folders.
Mon 7 … U/g … 80s dial survey and measurements … 3 men (RB*. RE, BH)
Tues 8 … U/g … 100s dial survey, 3 gates … 4 men (MS, RB, GB, RW)
Wed 9 … Technical College … Film show … Tellurometer instrument.
Thurs 10 … Off
Fri 11 … Checked scalings … o.k. Plotted 80s and 100s panels and stippled same. 1/5000 plans. R & FF base plan made up to date. Progress folders.
Mon 14 … Office … Several sets of R & FF prints coloured.
Tues 15 … U/g … 1s W/loo dial survey, pins re-established in 1s LH (RB*, RE, BH) Crush conditions
Wed 16 … U/g … Checking bases in Pit bottom in readiness for Correlation … 5 men (C Skeavington, Mal Smith, Jim Hanson, Jack Brown, RB)
Thurs 17 … Office … Manager’s plans to date.
Surface … Standardising steel bands on Silverhill baths roof … 3 men (C Skeavington, MS, RB)
Fri 18 … Surface … Levelled to borehole in Teversal Village … 2 men (RB*, GB)
Sat 19 … Surface … Hanging piano wires down No1 DC shaft (Saturday) … 6 men (C Skeavington, JW, CB, RB,GB, RW)
Pit Holidays Mon 21 July to Sat 2 Aug
In charge … Mal Smith holiday for 2 weeks (missed the Correlation but would use the results and method for his RICS exam)
Sun 20 … U/g … Weisbach correlation at Teversal No1 DC shaft (C Skeavington, Jack Brown, CB, RB, GB, RW) - (400 + 22 u/g)
Mon 21 … U/g … Weisbach correlation at No2 UC Shonkey shaft (Monday, pit holidays) … 6 men (C Skeavington, Jack Brown, Colin Hardy, RB, Peter Holmes, Denis Jackson)
Tues 22 … Surface … Base tied on to circuit … 6 men (C Skeavington, JW, RB, GB, DB, RW) …
Office … in afternoon … Glapwell Top Hard workings reduced to 1/5000 and 6 inch to a mile
Wed 23 … Surface … Triangulation angles (Watts 1 second theodolite) from satellite station and headgear station, catenary measuring … 6 men (C Skeavington, JW, RB, DB, RW, GB)
Thurs 24 … Surface … Theodolite survey to tie bases on circuit … 6 men C Skeavington, JW, RB, GB, DB, RW)
Fri 25 … Surface … Measured base in pit yard and angling with theodolite (RB*)
Mon 28 … U/g … 80s RH theodolite survey … 3 men (RB*, GB, RW)
Tues 29 … U/g … 100s LH and 100s DG theodolite survey … 3 men (RB*, GB, RW) (400 + 24 u/g)
Wed 30 …U/g … Dial survey from 1s DG to 1s LH for 2s thirling point, 2s heading survey … 3 men (RB*, GB, RW) … Surface … Sighting pole on No1 winding house roof re-fixed … (RB*)
Thurs 31 … Office … Ventilation negatives to date and prints, amended for 100s ventilation change. Calculated 80s and 2s surveys. Cleaned Watts 20 second theodolite.
Aug 1958 Jim Davies Undermanager retired (65) … Willis Bacon promoted from Afternoons to Undermanager
Fri 1 … Office … Finished Ventilation plans. Prints off all Manager’s plans for new set. Dust Zone plan etc. Plan showing Transfer points for Cost department.
Mon 4 … Bank Holiday and Tues 5 … Holiday
Wed 6 … U/g … Theodolite survey down South Plane Road into Fox’s Scouring, checking bases … 2 men (RB*, GB) - (405 + 22 u/g)
Thurs 7 … U/g … Re-established line in Fox’s Scouring with theodolite, checked measurement in 2s … 2 men (RB*, GB)
Fri 8 … Office … Calculating triangulation bearings for ‘trial point’.
Mon 11 … Office … Calculating triangulation, cutting points and triangles. Plotted for West and South.
Tues 12 … Office … Continued with correlation calculations.
Wed 13 … Office … Calculations of all distances to RHD (Reduced horizontal distance)
Thurs 14 … Mining report. Completed distances calculations. Updated overlay tracings and plotted 100s on Dunsil second copy plan. Coal sections for Price List.
Annual Leave Mon 18 – Sat 30 Bridlington
Sep 1958
Approx 7,500 tons per week
Mon 1 … U/g … 1s W/loo LH theodolite angling and measuring to mark thirling point … 3 men (RB*, GB, DB)
Tues 2 … U/g … 2s DG theodolite angling and measuring from South Plane Road … 3 men (RB*, GB, DB)

Photo:- Rear: Don Burton (British Railways), Robert Wain new Apprentice, Brian Hayes, new Linesman, Robert Elliott, Linesman, John Wilmot, Qualified Assistant on Group Staff. Front: Robert Bradley, self, Senior Apprentice, Geoff Beastall, Linesman.
Wed 3 … Office … 6 inch Dunsil plans. Pleasley workings to date.
Thurs 4 … U/g … Theodolite survey angling down Dunsil North Main Road … 5 men (MS, RB*, GB, DB, RW)
Fri 5 … Office … Top Hard 6 inch plans. Stippled Glapwell workings.
Mon 8 … Office … Top Hard 6 inch plans stippled. Reduced Sherwood workings from 1/2500.
Tues 9 … Office … Calculations for correlation.
Wed 10 … Office … Calculations for correlation.
Thurs 11 … Office … Calculations.
Surface … Measurements at Skegby Old Manor House … Ancient monument … 2 men (MS, RB)
Fri 12 … Office … Group Manager Mr J Frith’s Wall plans to date. Composite tracing … Sutton and Pleasley workings. Calculation of coal fillers required.
Mon 15 … Office … Calculating number of hours worked. 1/5000 plan updated.
Tues 16 … U/g … 1s LH and 1s DG and turned 80s RH, dial surveys … 2 men (RB*, DB) - (410 + 22 u/g)
Wed 17 … Office … Calculated and plotted 1s Waterloo on 1/2500, 1/5000 and 6 inch scales. Also Composite negative. Progress plans. Ventilation Officer, Jack Barker’s book to date.
Thurs 18 … Technical College
Fri 19 … Office … Updated Dunsil and Waterloo 6 inch roll plans. Title stencilled on Dunsil 6 inch flat sheet. Monthly book. Weekly progress folders and sheets.
Mon 22 … U/g … Catenary measuring across 40s DG to North Main Road … 4 men (MS, RB*, GB, DB)
Tues 23 … U/g … Catenary measuring down North Main Road … 4 men (MS, RB*, DB, RW)
Wed 24 … Office … 2 mining reports. Subsidence plans to date. Sherwood Top Hard on 6 inch plan.
Thurs 25 … Technical College
Fri 26 … Office … Estimate of coal fillers required on all faces. Monthly info. Conveyor belt figures, sections etc.
Mon 29 … Office … Completed calculations for estimate of coal fillers. These calculations were done all the time on Dunsil panels since I started work but generally done by the boss. It was imperative to measure on all faces where coal top was left up to form a good roof. It was plotted on the working plan. The lower the extraction height, the longer the stint. However a quick calculation … say 3ft 3in of coal, undercut 5ft 6in x 24 ft (8 yards stint) and then x 1.25 specific gravity of coal then divided by 27 (cu ft in a cubic yard) = 3.25 x 5.5 x 24 x 1.25 divided by 27 = 20 tons per man per shift. Length of face 250 yards some 8 yard stints where top coal of about 6 or 7 inches left up and some 7 yard stints where no top coal left up plus three x 4 yard stints. Chargeman had only 4 yards, doing organising etc and fast end man with cutter 4 yards, and gate end man 4 yards to allow for spillage in his stint. So say for example 120 yards of top coal left so divide 120 by 8 yards = 15 men. 150 yards at 7 yards (minus 3 men at 4 yards = 12 yards), so 250 minus 150 yards and 12 yards = 118 yards divided by 7 = 17, so total number on that face of 250 yards long is 15 + 3 + 17 = 35 men plus say 3 shotfirers (1 per 10 men) and 1 Deputy (who also could fire shots). Output from that face would be app 620 tons per day. A 5 day week would give 3,100 tons but there were losses. Coal thrown into gobbing or used for packers, or gate spillage say 1½ % = 45 tons so a realistic figure could be 3,050 tons per week from that panel.
Also completed Top Hard and Dunsil 6 inch (1/10560) flat sheets.
Tues 30 … U/g … 100s theodolite angling and measuring … 3 men (MS, RB*, RW) - (410 + 24 u/g)
Oct 1958
Wed 1 … U/g … 60s and 110s dial surveys, 5 gates … 4 men (RB*, RE, DB, RW).
Office … Calculated same.
Thurs 2 … Technical College.
Fri 3 … Office … Plotting 60s and 110s on plans. Scaling tracings for check on coal tonnages.
Mon 6 … Office … Scaling tracings. Calculated 100s district theodolite surveys.
Tues 7 … U/g … 80s and 100s dial surveys, 5 gates … 4 men (MS, RB*, RE. DB)
Wed 8 … U/g … 50s dial surveys, 2 gates … 4 men (RB*, DB, RE, Alan B (AB) new linesman.)
Thurs 9 … Technical College
Fri 10 … Levels copied and plotted on plans. Also contoured all plans to date. Plotted 80s district.
Mon 13 … Updated 1/5000 and 6 inch flat sheets. R & FF tracings. Sutton and Teversal progress. Deputy’s Districts, Egress, General Purpose, Electrical and Ventilation negatives. Manager’s tracings to date.
Tues 14 … Office … Continued Manager’s tracings and others.
Wed 15 … Office … John Morris, Electrician’s plans to date. Manager’s Deputy’s Districts.
In afternoon … Bi-annual Meeting of Surveyors at Bentinck Welfare … Subtense bar ….Derek Degg
Thurs 16 … Technical College
Fri 17 … Office … Plotting levels and contours and Overlay tracings to date. Progress folders.
Mon 20 … Office … Sutton and Teversal progress. Copied co-ordinates into survey books. Print off General purpose and coloured for Manager’s 1/5000 base plan.
Tues 21 … Office … Rating and coal calculation figures with C Skeavington. Further correlation calculations.
Wed 22 … U/g … New 10s face line established with dial, 100s monthly measurements and sections every 20 yards on 110s … (RB* and Brian Hayes)
Thurs 23 … Technical College … Traverse using a Watts 5’ dial.
Fri 24 … Office … Monthly info etc. Catenary measuring calculations for Main Road traverses. Tuition to GB.
Mon 27 … Office … Monthly information. 6 Mining reports.
Tues 28 … U/g … 10s face line checked, also Fox’s and sections every 10 yards on 110s 2 men (MS, RB) - (415 + 22 u/g)
Wed 29 … Office … Checking gradients of conveyors. Composite 1/5000 neg. Electrical plans. Copying monthly info. Checking S 300 level.
Thurs 30 … Technical College
Fri 31 … Holiday to Tues Nov 4
Nov 1958
Barry Bladon (BB) Apprentice started at Teversal, transferred from Pleasley (He would become my brother in law marrying my Wife’s youngest sister, but would divorce later).
Wed 5 … U/g … 1s dial survey, 2 gates … 4 men (RB*, GB, RE, BB)
Thurs 6 … Technical College
Fri 7 … Office … Plotted 1s Waterloo on 1/2500, 1/5000 and 6 inch scales.
Sat 8 … U/g … Pit bottom offset survey … 3 men (MS, RB, RW) (Saturday morning)
Mon 10 … Office … Progress plan for 1s. Electrical info to date with Vic Penford Charge Electrician. Printing machine adjustments etc.
Tues 11 … U/g … 1s levelling, 2 gates … 3 men (RB*, DB, RW)
Wed 12 … Office … Electrical plans to date. Waterloo levels copied. Pleasley Dunsil adjacent workings updated on all scales. Plans and Composite also.
Thurs 13 … Technical College
Fri 14 … Office … Electrical plans. Checking boreholes … some had wrong co-ordinates! Plotted some on Waterloo Overlays.
Sat 15 … U/g … No1 Pit bottom offset survey around shaft (Sat aft) … 3 men (MS, RB, GB)
Mon 17 … Office … Plotting boreholes and checking co-ordinates etc …
Meeting at Area HQ re Apprentice Surveyor’s Club.
Tues 18 … Checking tackle etc and maintenance.
Wed 19 … Exam
Thurs 20 … Technical College
Mon 24 … Office … Stencilling borehole information. Monthly information etc. Section sheets.
Tues 25 … Office … Electrical plans. Finished borehole information.
Wed 26 … Electrical plans, 2 sets finished and dispatched. Sections of steel arches for Mr Gubbins, Manager.
Thurs 27 … Office … Technical College
Fri 28 … U/g … 40s catenary measuring … 5 men (JW, RB, GB, RE, RW) … Office … Progress etc - (420 + 22 u/g)
Dec 1958
Tony Baines (TB) started as a Linesman Dec 14
Mon 1 … Office … Cleaning standard mine plans using cheese rubber and breadcrumbs. Progress folders. Contours plotted on plans.
Tues 2 … Office … Both Surveyors from Glapwell and Bramley Vale drift came to get Teversal workings and discuss. R & FF info for 80s put on tracing. Title on pit bottom tracing.
Wed 3 … Office … Gridded Waterloo sheet 43/ 4663 second copy. Traced surface for same. Reduced Skegby Lane from new 1/1250 plans to 1/2500. Sketch for 50s on 1/1250 for subsidence.
Thurs 4 … Technical College
Fri 5 … Office … Surface features on 1/5000 Dunsil finished also surface on Waterloo 43/4663 Second copy. Progress plans.
Mon 8 … Office … Progress folders. R & FF info to date. Plan for installation of Airdox firing at 50s and 100s.
Tues 9 … Office … Calculated and plotted gradient of new drift from North manrider to 1s Waterloo LH … 1in4. Calculations for catenary measuring.
Wed 10 … U/g … 1in4 grade line established at bottom of manrider … 2 men (RB*, RE)
Thurs 11 … Technical College
Fri 12 … Office … R & FF info. Gridded a new 1/2500 sheet for Second copy 1st Waterloo 43/4664. Progress folders.
Mon 15 … Office … Progress. Calculating catenary measurements. R & FF information
Tues 16 … U/g … 80s LH and 80s RH gates dial surveys … 4 men (RB*, RE, B Tinsley, and Tony Baines (TB) new linesman).
Wed 17 … Surface …to Silverhill office for info … (RB*) … Section of drift from Deep Hard to Piper for HMI … why me? Silverhill team too busy!
Thurs 18 … Technical College
Fri 19 …U/g … 1s LH theodolite angling and measuring … 4 men (MS, RB, GB, RW)
Mon 22 … U/g … Checking theodolite angles on South Main Road … 4 men (RB*, GB, DB, RW) … Office … Calculating 1s district surveys.
Tues 23 … U/g … 60s RH theodolite survey and measuring … 4 men (RB*, DB, GB, RW) - (425 + 22 u/g)
Wed 24 … Office … Calculated 60s RH survey … Party at Welfare.
Christmas Holiday … Thurs 25, Fri 26 … Annual Leave Mon 29 and Tues 30
Wed 31 … U/g … 60s and 110s dial surveys, 5 gates … 4 men (RB*, GB, DB, RW)
Manpower 756 u/g, 147 s/f
Abbreviations used:
LG or DG denotes Loader Gate or Delivery Gate.
LH denotes Left Hand Supply Gate. RH denotes Right Hand Gate, TG denotes Top Gate and BG is Bottom Gate. MG is Middle Gate. AW is Airway or Supply Gate. TG is Tail Gate, again a Supply Gate for materials. |